Tømrerfaget, skriftlig

The first 2 of 4 tasks · free, no sign-in

Before you start

  • Answer in Norwegian

    The tasks and your answer are in Norwegian, as on the exam. Tap an underlined term to see what it means, or tap Translate under a text.

  • Aids

    Every aid without internet is allowed, but not artificial intelligence. Name the sources you use.

  • Time

    No clock on the sample. In the exam you have 5 hours.

  • Evaluation

    You grade your answer against the examiner's criteria and an example answer, and get the grade worked out the way the examiner does.

Weighted mean of the tasks, as the examiners count.

You are halfway.

Buy access for the rest of this mock exam and as many new mock exams as you like, with a new case every time. Your answers and scores from the sample come with you.

Choose access

Review

Task 1 · 30 %

Lag en framdriftsplan for tømrerarbeidet på tilbygget. Vis rekkefølgen på arbeidsoperasjonene, når andre fag kommer inn, og begrunn rekkefølgen.

Translate

Make a work schedule for the carpentry on the extension. Show the order of tasks and when other trades will work, and explain the order.

Your answer

Example answer

Uke 1: Mottakskontroll av materialer, svillemembran og svill på ringmuren. Bjelkelag og gulv. Uke 2: Reise yttervegger og feste mot eksisterende vegg. Takbjelker og undertak. Uke 3: Vindsperre, vinduer og dør, lekter og kledning, taktekking. Nå er bygget tett. Uke 4: Elektriker og rørlegger legger føringer i veggene. Isolasjon og dampsperre. Uke 5: Innvendig kledning, himling og gulv. Uke 6: Listing, åpning inn til huset og sluttkontroll. Hvorfor: Tett bygg tidlig beskytter materialene mot fukt. Andre fag må inn før dampsperren, så vi slipper å lage hull i den. Vi åpner inn til huset sist, slik at familien får minst mulig støv og støy.

Translate

Week 1: Check materials on delivery. Fit a damp-proof strip and sole plate on the ring foundation. Build the floor joists and floor. Week 2: Raise the external walls and fix them to the existing wall. Build the roof joists and roof underlay. Week 3: Fit the wind barrier, windows and door, battens and cladding, and roof covering. The extension is now weather-tight. Week 4: The electrician and plumber install services inside the walls. Fit insulation and the vapour barrier. Week 5: Fit internal wall coverings, ceiling and floor. Week 6: Fit trim, open the wall into the house and do a final check. Why: Making the extension weather-tight early protects materials from moisture. The other trades must work before we fit the vapour barrier so they do not have to cut holes in it. We open the wall into the house last to limit dust and noise for the family.

Task 2 · 25 %

Gjør rede for hvordan ytterveggen i tilbygget bygges opp, sjikt for sjikt fra innsiden og ut. Forklar hvordan hvert sjikt påvirker varmegjennomgang og fukt.

Translate

Explain how the extension's external wall is built, layer by layer from inside to outside. Explain how each layer affects heat loss and moisture.

Your answer

Example answer

Innenfra: innvendig kledning, gjerne på en påforing med ekstra isolasjon, så dampsperre av plastfolie, bindingsverk 48 x 198 mm med 200 mm mineralull, vindsperre, lekter som gir en luftespalte, og utvendig kledning. Dampsperren ligger på den varme siden og hindrer at varm, fuktig inneluft trenger inn i veggen og kondenserer når den kommer mot den kalde siden. Skjøtene må klemmes eller tapes. Isolasjonen reduserer varmegjennomgangen. Vindsperren hindrer kald vind i å blåse gjennom isolasjonen, men den er dampåpen, så fukt som likevel kommer inn, slipper ut. Luftespalten lar regn som trenger bak kledningen renne ned og tørke ut.

Translate

From inside: an internal wall covering, perhaps on extra battens with more insulation, then a plastic-sheet vapour barrier, a 48 x 198 mm stud frame with 200 mm mineral wool, a wind barrier, battens that leave a ventilation gap, and external cladding. The vapour barrier is on the warm side. It stops warm, moist indoor air entering the wall and condensing near the cold side. Joints must be clamped or taped. Insulation reduces heat loss. The wind barrier stops cold air blowing through the insulation, but lets water vapour escape. The ventilation gap lets rainwater that gets behind the cladding drain and dry out.