Kjemiprosessfaget, skriftlig

The first 2 of 4 tasks · free, no sign-in

Before you start

  • Answer in Norwegian

    The tasks and your answer are in Norwegian, as on the exam. Tap an underlined term to see what it means, or tap Translate under a text.

  • Aids

    Every aid without internet is allowed, but not artificial intelligence. Name the sources you use.

  • Time

    No clock on the sample. In the exam you have 5 hours.

  • Evaluation

    You grade your answer against the examiner's criteria and an example answer, and get the grade worked out the way the examiner does.

Weighted mean of the tasks, as the examiners count.

You are halfway.

Buy access for the rest of this mock exam and as many new mock exams as you like, with a new case every time. Your answers and scores from the sample come with you.

Choose access

Review

Task 1 · 25 %

Planlegg oppstarten når kontroll av spyledysen er meldt muntlig ferdig, men kvittering på arbeidsordren mangler. Bruk planlagt mating 24 tonn per time og spylevann 12 kubikkmeter per time.

Translate

Plan the start-up when the spray nozzle inspection has been verbally reported as complete, but the work order has not been signed off. Use the planned feed rate of 24 tonnes per hour and spray-water flow rate of 12 cubic metres per hour.

Your answer

Example answer

Jeg starter ikke linjen bare på grunnlag av en muntlig melding. Først avklarer jeg med ansvarlig for arbeidsordren om dysekontrollen er avsluttet, verktøy er fjernet og anlegget er frigitt etter lokal prosedyre. Jeg kontrollerer deretter at sikt, renner, transportører og spylevann er klare, og at relevante instrumenter viser troverdige verdier. Oppstarten skjer i den rekkefølgen prosedyren angir, slik at materialet har en åpen vei gjennom anlegget. Under oppkjøring følger jeg både mating og vannmengde mot de planlagte verdiene på 24 tonn per time og 12 kubikkmeter per time. Jeg fører tidspunkt, avlesninger og eventuelle avklaringer i driftsloggen.

Translate

I do not start the line based only on a verbal report. First, I check with the person responsible for the work order whether the nozzle inspection is complete, tools have been removed and the plant has been released under the local procedure. I then check that the screen, chutes, conveyors and spray water are ready, and that relevant instruments show credible values. Start-up follows the sequence specified in the procedure so the material has an open route through the plant. During ramp-up, I monitor both feed and water flow against the planned values of 24 tonnes per hour and 12 cubic metres per hour. I enter the time, readings and any clarifications in the operating log.

Task 2 · 25 %

Laboratoriet ber om en planlagt stans for å ta en prøve fra produktstrømmen. Forklar start- og stopplogikken for siktelinjen med mineralmating 24 tonn per time og spylevann 12 kubikkmeter per time.

Translate

The laboratory requests a planned shutdown to take a sample from the product stream. Explain the start and stop sequence for the screening line with a mineral feed rate of 24 tonnes per hour and spray-water flow of 12 cubic metres per hour.

Your answer

Example answer

Dette er en planlagt stans, ikke en grunn til å bruke nødstopp. Jeg avtaler tidspunkt med laboratoriet og følger anleggets sekvens for kontrollert nedkjøring. Normalt må tilførselen av mineral opphøre før utstyr nedstrøms stoppes, slik at renner og sikt ikke blir stående fulle. Hvordan spylevann og transportører stoppes, bestemmes av den lokale prosedyren. Jeg bekrefter på skjerm og ved tillatte observasjonspunkter at materialflyten er opphørt, og registrerer siste avlesninger. Prøvetaking skjer etter gjeldende arbeidsmåte. Før ny start må området være frigitt, utstyr og instrumenter være klare, og startsekvensen følges på nytt. En akutt fare ville krevd varslings- og nødprosedyren i stedet.

Translate

This is a planned shutdown, not a reason to use the emergency stop. I agree a time with the laboratory and follow the plant's sequence for controlled shutdown. Normally, the mineral feed must stop before downstream equipment is stopped so that chutes and the screen are not left full. How the spray water and conveyors are stopped is determined by the local procedure. I confirm on the display and at permitted observation points that material flow has stopped, and record the final readings. Sampling takes place according to the applicable work procedure. Before restarting, the area must be released, equipment and instruments must be ready, and the start sequence must be followed again. An immediate hazard would instead require the notification and emergency procedures.