AMF3103 Free trial
English

AMF3103

Anleggsmaskinførerfaget, skriftlig

The first 2 of 4 tasks · free, no sign-in

Before you start

  • Answer in Norwegian

    The tasks and your answer are in Norwegian, as on the exam. Tap an underlined term to see what it means, or tap Translate under a text.

  • Aids

    Every aid without internet is allowed, but not artificial intelligence. Name the sources you use.

  • Time

    No clock on the sample. In the exam you have 5 hours.

  • Evaluation

    You grade your answer against the examiner's criteria and an example answer, and get the grade worked out the way the examiner does.

Weighted mean of the tasks, as the examiners count.

You are halfway.

Buy access for the rest of this mock exam and as many new mock exams as you like, with a new case every time. Your answers and scores from the sample come with you.

Choose access

Review

Task 1 · 25 %

Leverandøren kommer 15 minutter før avsperringen er ferdig. Verkstedeieren har bestemt at gangpassasjen skal ha 1,5 m fri bredde. Mina finner dokumentasjonen på opplæringen, men maskinspesifikk familiarisering er ikke avklart. Lag en kort sikker jobbanalyse: Prioriter farene og konsekvensene, velg tiltak for passasjen, bestem hvordan leveransen håndteres, og fordel ansvar for kontroll og oppstart. Forklar hvilke opplæringsforhold som må avklares, og når arbeidet skal stanses.

Translate

The supplier arrives 15 minutes before the barriers are complete. The workshop owner has specified that the pedestrian passage must have a clear width of 1,5 m. Mina finds her training documentation, but machine-specific familiarisation has not been confirmed. Prepare a short safe job analysis [sikker jobbanalyse]: prioritise the hazards and consequences, choose measures for the passage, decide how to handle the delivery, and assign responsibility for checks and starting work. Explain which training matters must be clarified and when work must stop.

Your answer

Example answer

Jeg stanser planlagt lossing og maskinbruk. Første prioritet er å hindre at gående kommer inn i maskinens arbeidsområde eller mellom lastebilen og faste konstruksjoner. Mulige konsekvenser er påkjørsel og klemskade. Den bestilte frie bredden på 1,5 m kontrolleres fysisk, men bredden alene gjør ikke passasjen trygg. Avsperringen må også holde personer utenfor maskinens faktiske arbeids- og svingområde. Leverandøren henvises til en avklart oppstillingsplass som ikke blokkerer passasjen eller verkstedets adkomst. Finnes ikke en slik plass, avtaler arbeidslederen ny leveringstid. Tidspresset gir ikke grunnlag for å losse i et usikret område. Arbeidslederen avklarer nødvendig sertifisert sikkerhetsopplæring og kontrollerer dokumentasjonen. Minas dokumenterte opplæring erstatter ikke familiarisering med betjening, sikkerhetsfunksjoner og begrensninger på akkurat denne maskinen. Mina gjennomfører nødvendig familiarisering før bruk og kontrollerer maskinen før oppstart. Grunnforhold og ledningsopplysninger må også være avklart før terrenginngrep. Arbeidslederen frigir området først når kontrollpunktene i sikker jobbanalysen er lukket. Arbeidet stoppes ved brutt avsperring, personer i faresonen eller nye grunnforhold. Forsinkelsen koster tid, men reduserer risikoen for alvorlig skade.

Translate

I stop the planned unloading and machine use. The first priority is to prevent pedestrians from entering the machine's working area or the space between the lorry and fixed structures. Possible consequences are being struck by a vehicle and crush injuries. The specified clear width of 1,5 m is physically checked, but width alone does not make the passage safe. The barriers [avsperring] must also keep people outside the machine's actual working and swing areas [svingområde]. The supplier is directed to an agreed standing area that does not block the passage or access to the workshop. If no such area is available, the site supervisor [arbeidsleder] arranges a new delivery time. Time pressure is not a reason to unload in an unsecured area. The site supervisor establishes the required certified safety training [sertifisert sikkerhetsopplæring] and checks the documentation. Mina's documented training does not replace familiarisation with the controls, safety functions and limitations of this particular machine. Mina completes the necessary familiarisation before use and checks the machine before starting. Ground conditions and utility information must also be clarified before ground disturbance. The site supervisor clears the area for work only when the checkpoints in the safe job analysis have been closed out. Work stops if barriers are breached, people enter the danger zone or new ground conditions are encountered. The delay costs time, but reduces the risk of serious injury.

Task 2 · 25 %

Tegningen angir 12 m ganger 8 m, men inneholder verken ferdighøyde, fall eller toleranse. Det finnes 1 fastmerke utenfor arbeidsområdet. Skriv en arbeidsbeskrivelse som viser arealberegning, utsetting og sikring av punkter, beskyttelse av gangpassasjen og arbeidsrekkefølge. Ta med ledningsavklaring og en begrunnet kontroll av maskinens egnethet. Bestem hva Mina kan gjøre før opplysningene er avklart, og hvordan høyder, fall, toleranser og sluttkontroll skal dokumenteres.

Translate

The drawing specifies 12 m by 8 m, but contains no finished level, slope or tolerance. There is 1 benchmark [fastmerke] outside the work area. Write a method statement [arbeidsbeskrivelse] showing the area calculation, setting out [utsetting] and protection of points, protection of the pedestrian passage and the work sequence. Include utility checks and a reasoned assessment of the machine's suitability. Decide what Mina can do before the information is confirmed, and how levels, slopes, tolerances and the final inspection will be documented.

Your answer

Example answer

Jeg beregner fotavtrykket til 12 m × 8 m = 96 m². Dette er plassens tegnede areal, ikke et grunnlag for å anslå produksjon. Jeg kontrollerer målene mot tegningen, merker hjørnene og kontrollerer plasseringen med diagonalmål. Punktene og fastmerket sikres mot påkjørsel og flytting. Gangpassasjen skal ikke inngå i arbeidsarealet. Før terrenginngrep avklares ledninger, grunnforhold og sikring. Gravemaskinen vurderes mot tilgjengelig adkomst, grunnens bæreevne, nødvendig rekkevidde, arbeidskapasitet og produsentens begrensninger. At maskinen er tilgjengelig, er ikke tilstrekkelig begrunnelse. Egnet skuffe og arbeidsstilling velges først når oppdraget og forholdene er avklart. Mina kan kontrollere dokumenter, gjennomføre sikker befaring og foreta utsetting fra sikre steder. Hun skal ikke finavrette etter en antatt høyde. Arbeidslederen må innhente ferdighøyde, fallretning, fallkrav og toleranse fra den som har ansvar for beskrivelsen. Deretter etableres høydekontroll fra fastmerket, og massene bearbeides etter den avklarte beskrivelsen. Målepunkter, måleresultater og tegningsversjon registreres. Manglende krav behandles som en avklaring, ikke som frihet til å improvisere. Venting forsinker oppstarten, men forebygger feil fall, vannansamling og kostbar omarbeiding.

Translate

I calculate the footprint as 12 m × 8 m = 96 m². This is the area shown on the drawing, not a basis for estimating productivity. I check the dimensions against the drawing, mark the corners and check the position using diagonal measurements. The points and benchmark [fastmerke] are protected against vehicle impact and movement. The pedestrian passage must not form part of the work area. Before ground disturbance, utilities, ground conditions and safety measures are clarified. The excavator is assessed against available access, the ground's bearing capacity [bæreevne], required reach, working capacity and the manufacturer's limitations. The machine being available is not sufficient justification. A suitable bucket and working position are chosen only once the task and conditions are confirmed. Mina can check documents, carry out a safe site inspection and set out points from safe locations. She must not carry out final grading [finavretting] to an assumed level. The site supervisor [arbeidsleder] must obtain the finished level, slope direction, slope requirement and tolerance from the person responsible for the specification. Level checks are then established from the benchmark, and the materials are worked according to the confirmed specification. Measurement points, results and drawing version are recorded. Missing requirements are treated as matters requiring clarification, not as freedom to improvise. Waiting delays the start, but prevents incorrect slopes, water pooling and costly rework.